https://ferns.odf.oregon.gov/E-Notification/noap/195532/Report/Summary
Operator:
Thomas Ireland
Cascade West, Inc.
PO Box 338
Dillard, Oregon 97432
(541) 817-6119
Activity: Clearcut/Overstory Removal
Start: 2/12/2025spaceEnd: 12/31/2025
Completion Status: Open
Method(s): Cable,
Ground
Quantity: 1200.00 MBF
Operator:
Thomas Ireland
Cascade West, Inc.
PO Box 338
Dillard, Oregon 97432
(541) 817-6119
Activity: Use of Fire
Start: 3/5/2025spaceEnd: 12/31/2025
Completion Status: Open
Method(s): Burn Piles
Quantity: 114.00 Acres
NOTES:
1) Both Units: All streams within units are Small Type-Np. Streams that are tributaries to Munger Creek shall have a
35′ (no-cut) RMA for 1150′ upstream from the confluence with Munger Creek. Beyond 1150′, streams shall have a 35′
R-ELZ buffer, which allow merchantable timber to be harvested up to the high water mark on Type-N streams,
however understory vegetation and <6″ conifer must be retained within 35′ of stream on both sides.
2) This unit is subject to the 2 up/2 down LT and LWD rules.
3) Ensure units do not exceed 120 acres in size.
4) No conflict with other protected resources.
If you have any questions regarding stream RMA’s please contact George Sheppard at 541 471-4243.